Briarwood Crossing Phase 2 Detention Pond Improvements
Briarwood Crossing Drive & Learning Tree Lane, Rosenberg, TX 77494, Rosenberg, TX, 77494
Completed100%
๐Project Metrics
TDLR #TABS2022002103$6.2M
Project Value
25,561
Square Feet
$241/sqft
Cost/SqFt
2y 1mo
Duration
Registered:Sep 30, 2021
Start:Nov 22, 2021
Target:Dec 1, 2023
๐
Project Closed
Project has been completed and closed
๐Scope of Work
Sidewalks, Tree Planting, Park Benches, Trash Receptacles, Fine Grading, Hydromulch, & Irrigation System
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
September 30, 2021
Construction Start
November 22, 2021
Expected Completion
December 1, 2023
๐Related Projects
๐คSame Owner
$2.3M totalBriarwood Crossing Courageous Trail Landscape Improvements
Rosenbergยท$1.2M
Briarwood Crossing Section 18 Landscape Improvements
Rosenbergยท$362K
Morton Creek Ranch Sec 30 and Streetscape Adj to Sec 25 landscape improvements
Katyยท$519K
Briarwood Crossing Ph 2 Sec 12 Landscape Improvements
Rosenbergยท$265K
Property Owner
๐ค
WOODMERE DEVELOPMENT COMPANY
Contact: Andrew Rue
4 projects ยท $2.3M
View company profile
15915 Katy Freeway Suite 405, Houston, Texas 77094
Design Firm
๐๏ธ
KGA DeForest Design, LLC
4 projects ยท $1.8M
View company profile
24275 Katy Freeway suite 300, Katy, Texas 77494