🏁Project Closed🏗️ New Construction💵 This project is privately funded, on private land for private use.
Centrex Flooring, Inc. - New Office - Whse
5475 FM 902, Gainesville, TX 76240, Gainesville, TX, 76240
Completed100%
📊Project Metrics
TDLR #TABS2022003885$1.6M
Project Value
34,000
Square Feet
$47/sqft
Cost/SqFt
6 months
Duration
Registered:Oct 26, 2021
Start:Jul 1, 2021
Target:Dec 15, 2021
🏁
Project Closed
Project has been completed and closed
📋Scope of Work
Office/Whse - Metal Building
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
📅Compliance Timeline
Project Registered
October 26, 2021
Construction Start
July 1, 2021
Expected Completion
December 15, 2021