🏁Project Closed🔧 Renovation/Alteration💵 This project involves public funds, public land, or is a Federally funded roadway project.

City of Bryan Palasota Drive, Ph 2 Reconstruction

Palasota Dr. @ Cottonwood Branch to W. 28th St, Bryan, TX 77803, Bryan, TX, 77803
Completed100%

📊Project Metrics

TDLR #TABS2022004668
$2.0M
Project Value
261,360
Square Feet
$8/sqft
Cost/SqFt
10 months
Duration
Registered:Nov 5, 2021
Start:Jan 1, 2022
Target:Oct 31, 2022
🏁

Project Closed

Project has been completed and closed

📋Scope of Work

Removal and reconstruct Palasota Drive including sidewalks, cross walks and curb ramps

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

📅Compliance Timeline

Project Registered
November 5, 2021
Construction Start
January 1, 2022
Expected Completion
October 31, 2022

Quick Actions

TDLR ID: TABS2022004668

Design Firm

🏛️
GOODWIN LASITER STRONG ENGINEERS
View company profile
4077 Cross Park Dr., Suite 100, Bryan, Texas 77802

Registered Accessibility Specialist

📋
EDDIE,HARE
RAS #8
5855 FOSTER RD, BRYAN, TX 77807