🏁Project Closed🏗️ New Construction💵 This project is privately funded, on private land for private use.
Peoples State Bank
5858 Hwy 27, Center Point, TX 78010, Center Point, TX, 78010
Completed100%
📊Project Metrics
TDLR #TABS2022005031$750K
Project Value
27,963
Square Feet
$27/sqft
Cost/SqFt
11 months
Duration
Registered:Nov 10, 2021
Start:Jan 1, 2021
Target:Dec 1, 2021
🏁
Project Closed
Project has been completed and closed
📋Scope of Work
Install modular buildings for branch bank
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
📅Compliance Timeline
Project Registered
November 10, 2021
Construction Start
January 1, 2021
Expected Completion
December 1, 2021