Inspection Complete🏗️ New Construction💵 This project is privately funded, on private land for private use.

Toro Coffee 10619 Culebra

10619 Culebra Rd., San Antonio, TX 78251, San Antonio, TX, 78251
Final Inspection85%

📊Project Metrics

TDLR #TABS2022005270
$375K
Project Value
450
Square Feet
$833/sqft
Cost/SqFt
2 months
Duration
Registered:Nov 13, 2021
Start:Dec 20, 2021
Target:Feb 16, 2022

Inspection Complete

Final inspection completed, awaiting project closure

📋Scope of Work

Develop a 14000 sf site, Install a 450 sf drive thru coffee building. Handicap accessible. No food service, drinks only. Drive thru only

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

📅Compliance Timeline

Project Registered
November 13, 2021
Inspection Complete
February 16, 2022
Construction Start
December 20, 2021
Expected Completion
February 16, 2022