📝Review Complete🏗️ New Construction💵 This project is privately funded, on private land for private use.
Sherry Lane
k1356 Sherry Lane, Desoto, TX 75115, Desoto, TX, 75115
Construction50%
📊Project Metrics
TDLR #TABS2022007197$50K
Project Value
1,000
Square Feet
$50/sqft
Cost/SqFt
8 months
Duration
Registered:Dec 13, 2021
Start:Oct 1, 2021
Target:May 31, 2022
📝
Review Complete
Design review complete, construction may proceed
📋Scope of Work
Trucking Dispatch
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
📅Compliance Timeline
Project Registered
December 13, 2021
Construction Start
October 1, 2021
Expected Completion
May 31, 2022
Property Owner
👤
GERMAL LOPEZ
Contact: German Lopez
View company profile
135y Sherry Lane, Desoto, Texas 75115