๐ŸProject Closed๐Ÿ—๏ธ New Construction๐Ÿ’ต This project is privately funded, on private land for private use.

Allsup's Colorado City #102386

947 I-20 Highway, Colorado City, TX 79572, Colorado City, TX, 79572
Completed100%

๐Ÿ“ŠProject Metrics

TDLR #TABS2022008305
$1.2M
Project Value
6,277
Square Feet
$191/sqft
Cost/SqFt
3 months
Duration
Registered:Dec 29, 2021
Start:Feb 7, 2022
Target:May 8, 2022
๐Ÿ

Project Closed

Project has been completed and closed

๐Ÿ“‹Scope of Work

All Architectural, Structural, MEP work of New Construction Facility

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
December 29, 2021
Construction Start
February 7, 2022
Expected Completion
May 8, 2022