Inspection Complete๐ง Renovation/Alteration๐ต This project involves public funds, public land, or is a Federally funded roadway project.
Allen High School Fire Lane Replacement
300 Rivercrest Blvd, Allen, TX 75002, Allen, TX, 75002
Final Inspection85%
๐Project Metrics
TDLR #TABS2022011425$70K
Project Value
8,000
Square Feet
$9/sqft
Cost/SqFt
2 months
Duration
Registered:Feb 10, 2022
Start:Jun 1, 2022
Target:Aug 2, 2022
โ
Inspection Complete
Final inspection completed, awaiting project closure
๐Scope of Work
Removal and replacement of sidewalks and barrier free ramps adjacent to existing fire lane pavement that is being replaced
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
February 10, 2022
Construction Start
June 1, 2022
Expected Completion
August 2, 2022
๐Related Projects
Property Owner
๐ค
Allen ISD
Contact: Brandon Boyter
4 projects ยท $117.2M
View company profile
1451 N Watters Dr, Allen, Texas 75013