๐Ÿ“Review Complete๐Ÿ—๏ธ New Construction๐Ÿ’ต This project is privately funded, on private land for private use.

4 Sons Trucking

15200 S. IH35, Bruceville, TX 76630, Bruceville, TX, 76630
Construction50%

๐Ÿ“ŠProject Metrics

TDLR #TABS2022012187
$925K
Project Value
10,453
Square Feet
$88/sqft
Cost/SqFt
11 months
Duration
Registered:Feb 21, 2022
Start:Mar 31, 2022
Target:Feb 28, 2023
๐Ÿ“

Review Complete

Design review complete, construction may proceed

๐Ÿ“‹Scope of Work

Truck repair shop, offices, break room, restrooms, parts area and parking

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
February 21, 2022
Construction Start
March 31, 2022
Expected Completion
February 28, 2023