๐Review Complete๐๏ธ New Construction๐ต This project involves public funds, public land, or is a Federally funded roadway project.
FM 2061 (S McColl Rd)
From: SH 107 To: Trenton Rd, Mcallen, TX 78504, Mcallen, TX, 78504
Construction50%
๐Project Metrics
TDLR #TABS2022012585$637K
Project Value
94,032
Square Feet
$7/sqft
Cost/SqFt
7 months
Duration
Registered:Feb 24, 2022
Start:May 1, 2026
Target:Dec 1, 2026
Remaining:339 days
๐
Review Complete
Design review complete, construction may proceed
๐Scope of Work
Construction of sidewalks and curb ramps.
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
February 24, 2022
Construction Start
May 1, 2026
Expected Completion
December 1, 2026
๐Related Projects
Property Owner
๐ค
TxDOT District: Pharr
Contact: Jose L. Cardenas, P.E.
4 projects ยท $80.1M
View company profile
600 W Interstate 2, Pharr, Texas 78577