📝Review Complete🔧 Renovation/Alteration💵 This project is privately funded, on private land for private use.

Mary Jane CBD Dispensary

4230 N Foster Rd Ste.#106, San Antonio, TX 78247, San Antonio, TX, 78247
Construction50%

📊Project Metrics

TDLR #TABS2022014144
$124K
Project Value
2,200
Square Feet
$56/sqft
Cost/SqFt
9 months
Duration
Registered:Mar 15, 2022
Start:Mar 15, 2022
Target:Dec 1, 2022
📝

Review Complete

Design review complete, construction may proceed

📋Scope of Work

Interior Finish Out

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

📅Compliance Timeline

Project Registered
March 15, 2022
Construction Start
March 15, 2022
Expected Completion
December 1, 2022