๐Ÿ“Review Complete๐Ÿ—๏ธ New Construction๐Ÿ’ต This project is privately funded, on private land for private use.

Shell Building

Skyline Dr. & Hwy 380, Mckinney, TX 75071, Mckinney, TX, 75071
Construction50%

๐Ÿ“ŠProject Metrics

TDLR #TABS2022014317
$2.3M
Project Value
14,462
Square Feet
$159/sqft
Cost/SqFt
1y 11mo
Duration
Registered:Mar 17, 2022
Start:May 1, 2022
Target:Mar 30, 2024
๐Ÿ“

Review Complete

Design review complete, construction may proceed

๐Ÿ“‹Scope of Work

Single story shell building

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
March 17, 2022
Construction Start
May 1, 2022
Expected Completion
March 30, 2024