โœ…Inspection Complete๐Ÿ—๏ธ New Construction๐Ÿ’ต This project is privately funded, on private land for private use.

COMMUNITY NATIONAL BANK

11807 SLIDE ROAD, Lubbock, TX 79424, Lubbock, TX, 79424
Final Inspection85%

๐Ÿ“ŠProject Metrics

TDLR #TABS2022015193
$6.6M
Project Value
10,827
Square Feet
$610/sqft
Cost/SqFt
1y 1mo
Duration
Registered:Mar 29, 2022
Start:Apr 1, 2022
Target:May 1, 2023
โœ…

Inspection Complete

Final inspection completed, awaiting project closure

๐Ÿ“‹Scope of Work

NEW BANKING FACILITY & SITE IMPROVEMENTS

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
March 29, 2022
Construction Start
April 1, 2022
Expected Completion
May 1, 2023