โœ…Inspection Complete๐Ÿ—๏ธ New Construction๐Ÿ’ต This project is privately funded, on private land for private use.

SST Sugar Land Atheltic Facilities Addition - Soccer Field and Basketball Court

10007 Clodine Rd, Richmond, TX 77407, Richmond, TX, 77407
Final Inspection85%

๐Ÿ“ŠProject Metrics

TDLR #TABS2022015824
$180K
Project Value
19,800
Square Feet
$9/sqft
Cost/SqFt
4 months
Duration
Registered:Apr 5, 2022
Start:May 18, 2022
Target:Sep 15, 2022
โœ…

Inspection Complete

Final inspection completed, awaiting project closure

๐Ÿ“‹Scope of Work

Installation of a synthetic turf soccer field and post-tensioned concrete slab for an outdoor basketball court. Much of the work is site work and grading, then the pouring of concrete, followed by the surfacing of the court & field.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
April 5, 2022
Construction Start
May 18, 2022
Expected Completion
September 15, 2022

๐Ÿ”—Related Projects