๐ŸProject Closed๐Ÿ—๏ธ New Construction๐Ÿ’ต This project involves public funds, public land, or is a Federally funded roadway project.

PSJA ISD Athletic Facilities Improvements - PSJA North Early College HS

500 E. Nolana Loop, Pharr, TX 78577, Pharr, TX, 78577
Completed100%

๐Ÿ“ŠProject Metrics

TDLR #TABS2022017651
$1.8M
Project Value
100,000
Square Feet
$18/sqft
Cost/SqFt
4 months
Duration
Registered:Apr 27, 2022
Start:May 2, 2022
Target:Sep 1, 2022
๐Ÿ

Project Closed

Project has been completed and closed

๐Ÿ“‹Scope of Work

Convert grass field to synthetic turf, reconstruct existing track surface. New scoreboards, play clocks, misc. concrete pavement & fencing, hose bibbs, storm drainage, elec. conduits & power, var. new LJ, TJ, HJ, pole vault events

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
April 27, 2022
Construction Start
May 2, 2022
Expected Completion
September 1, 2022