๐ŸProject Closed๐Ÿ—๏ธ New Construction๐Ÿ’ต This project involves public funds, public land, or is a Federally funded roadway project.

CDBG Jefferson St sidewalk - San Bernardo Ave to Lee Ave

Jefferson St, Laredo, TX 78040, Laredo, TX, 78040
Completed100%

๐Ÿ“ŠProject Metrics

TDLR #TABS2022017702
$233K
Project Value
12,940
Square Feet
$18/sqft
Cost/SqFt
3 months
Duration
Registered:Apr 27, 2022
Start:Apr 29, 2022
Target:Jul 29, 2022
๐Ÿ

Project Closed

Project has been completed and closed

๐Ÿ“‹Scope of Work

Construction of sidewalks, ramps, and driveways as needed.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
April 27, 2022
Project Closed
July 29, 2022
Construction Start
April 29, 2022
Expected Completion
July 29, 2022