๐Ÿ“Review Complete๐Ÿ”ง Additions to Existing Building๐Ÿ’ต This project is privately funded, on private land for private use.

CGT Lab Expansion / TI

695 Holcan Drive, New Braunfels, TX 78130, New Braunfels, TX, 78130
Construction50%

๐Ÿ“ŠProject Metrics

TDLR #TABS2022017795
$450K
Project Value
3,350
Square Feet
$134/sqft
Cost/SqFt
4 months
Duration
Registered:Apr 28, 2022
Start:Jun 15, 2022
Target:Oct 14, 2022
๐Ÿ“

Review Complete

Design review complete, construction may proceed

๐Ÿ“‹Scope of Work

Tenant Improvement to expand existing Testing Lab within existing building footprint.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
April 28, 2022
Construction Start
June 15, 2022
Expected Completion
October 14, 2022