South San Antonio ISD West Campus HS - Phase IV Renovations - Cafeteria Package

5622 Ray Ellison Blvd, San Antonio, TX 78242, San Antonio, TX, 78242
Final Inspection85%

๐Ÿ“ŠProject Metrics

TDLR #TABS2022022422
$1.0M
Project Value
11,700
Square Feet
$85/sqft
Cost/SqFt
3 months
Duration
Registered:Jun 27, 2022
Start:Aug 1, 2022
Target:Oct 31, 2022
โœ…

Inspection Complete

Final inspection completed, awaiting project closure

๐Ÿ“‹Scope of Work

Remodel of existing storage space into new school cafeteria

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
June 27, 2022
Inspection Complete
October 31, 2022
Construction Start
August 1, 2022
Expected Completion
October 31, 2022