Woods Distribution at Synergy 300

I-35 and Golden Triangle, Fort Worth, TX 76177, Fort Worth, TX, 76177
Completed100%

๐Ÿ“ŠProject Metrics

TDLR #TABS2022022569
$2.4M
Project Value
3,803
Square Feet
$626/sqft
Cost/SqFt
5 months
Duration
Registered:Jun 28, 2022
Start:Aug 1, 2022
Target:Dec 31, 2022
๐Ÿ

Project Closed

Project has been completed and closed

๐Ÿ“‹Scope of Work

T.I. Work = 3675 sf / Remote RR = 128 sf

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
June 28, 2022
Construction Start
August 1, 2022
Expected Completion
December 31, 2022

Quick Actions

TDLR ID: TABS2022022569

Design Firm

Registered Accessibility Specialist

๐Ÿ“‹
CONNIE,FLEMING
RAS #140
PO BOX 1657, BRIDGEPORT, TX 76426

Tenant

๐Ÿข
Bill Woods