๐ŸProject Closed๐Ÿ—๏ธ New Construction๐Ÿ’ต This project is privately funded, on private land for private use.

Creek Rush Amenity Center

2800 TURNING CREEK LN, Fulshear, TX 77441, Fulshear, TX, 77441
Completed100%

๐Ÿ“ŠProject Metrics

TDLR #TABS2022023923
$6.6M
Project Value
3,600
Square Feet
$1.83K/sqft
Cost/SqFt
1y 8mo
Duration
Registered:Jul 18, 2022
Start:Sep 1, 2022
Target:Apr 30, 2024
๐Ÿ

Project Closed

Project has been completed and closed

๐Ÿ“‹Scope of Work

New 3,605 gsf (5,270 gsf under roof) single-story amenity building for the exclusive use of the residents of the Cross Creek Ranch community, including site improvements and utilities.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
July 18, 2022
Construction Start
September 1, 2022
Expected Completion
April 30, 2024

Quick Actions

TDLR ID: TABS2022023923

Registered Accessibility Specialist

๐Ÿ“‹
KEITH,LESTER
RAS #341
20035 HILLTOP RANCH DR, MONTGOMERY, TX 77316