๐Project Closed๐๏ธ New Construction๐ต This project involves public funds, public land, or is a Federally funded roadway project.
Ruby Haliburton Maintenance & Transportation Facility
4001 Leonard Road, Bryan, TX 77807, Bryan, TX, 77807
Completed100%
๐Project Metrics
TDLR #TABS2022024566$35.0M
Project Value
100,000
Square Feet
$350/sqft
Cost/SqFt
2 years
Duration
Registered:Jul 26, 2022
Start:Oct 4, 2022
Target:Sep 15, 2024
๐
Project Closed
Project has been completed and closed
๐Scope of Work
New transportation center with offices, warehouse, and bus maintenance shop and a separate new Maintenance center with offices, training rooms, shops and warehouse storage.
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
July 26, 2022
Construction Start
October 4, 2022
Expected Completion
September 15, 2024