๐Ÿ“Review Complete๐Ÿ—๏ธ New Construction๐Ÿ’ต This project is privately funded, on private land for private use.

FM 758 Turn Lanes

FM 758 On FM 758 0.87 miles northeast of SH 46, New Braunfels, TX 78130, New Braunfels, TX, 78130
Construction50%

๐Ÿ“ŠProject Metrics

TDLR #TABS2022024805
$132K
Project Value
20,200
Square Feet
$7/sqft
Cost/SqFt
5 months
Duration
Registered:Jul 28, 2022
Start:Oct 17, 2022
Target:Mar 20, 2023
๐Ÿ“

Review Complete

Design review complete, construction may proceed

๐Ÿ“‹Scope of Work

This is a roadway widening project to add turn lanes into a residential development which will be adding a pedestrian shared-use-path all along the front of the development.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
July 28, 2022
Construction Start
October 17, 2022
Expected Completion
March 20, 2023