โœ…Inspection Complete๐Ÿ—๏ธ New Construction๐Ÿ’ต This project is privately funded, on private land for private use.

Club Car Wash Melissa Texas

Hwy 121 & FM 2933, Melissa, TX 75454, Melissa, TX, 75454
Final Inspection85%

๐Ÿ“ŠProject Metrics

TDLR #TABS2022026584
$1.8M
Project Value
5,671
Square Feet
$317/sqft
Cost/SqFt
1y 1mo
Duration
Registered:Aug 19, 2022
Start:Nov 1, 2022
Target:Dec 7, 2023
โœ…

Inspection Complete

Final inspection completed, awaiting project closure

๐Ÿ“‹Scope of Work

Construct new 146' long tunnel style car wash facility to include office, toilet, storage, and cashier, equipment room and wash tunnel.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
August 19, 2022
Inspection Complete
December 7, 2023
Construction Start
November 1, 2022
Expected Completion
December 7, 2023

๐Ÿ“Location & Views

Open in MapsGet Directions|33.16096, -96.60610

Get alerts for Collin

Daily email when new projects start nearby.

Start Alerts - $19/mo

Download project data

Get curated lists of projects with full contact info.

Browse Data Lists