โœ…Inspection Complete๐Ÿ—๏ธ New Construction๐Ÿ’ต This project is privately funded, on private land for private use.

GCP

200 Planters Road, Sunnyvale, TX 75182, Sunnyvale, TX, 75182
Final Inspection85%

๐Ÿ“ŠProject Metrics

TDLR #TABS2023001012
$8.5M
Project Value
350,943
Square Feet
$24/sqft
Cost/SqFt
5 months
Duration
Registered:Sep 15, 2022
Start:Oct 3, 2022
Target:Mar 6, 2023
โœ…

Inspection Complete

Final inspection completed, awaiting project closure

๐Ÿ“‹Scope of Work

First time finish out of office in industrial building

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
September 15, 2022
Construction Start
October 3, 2022
Expected Completion
March 6, 2023