โœ…Inspection Complete๐Ÿ—๏ธ New Construction๐Ÿ’ต This project involves public funds, public land, or is a Federally funded roadway project.

Milam Street Reconstruction

400 Block to 1200 Block N. Milam St, Seguin, TX 78155, Seguin, TX, 78155
Final Inspection85%

๐Ÿ“ŠProject Metrics

TDLR #TABS2023004715
$7.0M
Project Value
18,000
Square Feet
$389/sqft
Cost/SqFt
2y 3mo
Duration
Registered:Nov 4, 2022
Start:Jan 1, 2023
Target:Mar 31, 2025
โœ…

Inspection Complete

Final inspection completed, awaiting project closure

๐Ÿ“‹Scope of Work

Replace sidewalks and install new sidewalks along Milam Street including accessible ramps, and miscellaneous appurtenances.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
November 4, 2022
Construction Start
January 1, 2023
Expected Completion
March 31, 2025

Quick Actions

TDLR ID: TABS2023004715

Design Firm

๐Ÿ›๏ธ
TRC Companies, Inc
View all projects
809 E. Court St Suite 106, Seguin, Texas 78155

Registered Accessibility Specialist

๐Ÿ“‹
JESUS E,LARDIZABAL
RAS #1051
3616 FAR WEST BLVD # 117288, AUSTIN, TX 78731