📝Review Complete🏗️ New Construction💵 This project is privately funded, on private land for private use.

CC GASKET & FASTENER STORAGE BUILDING

402 WESTCHESTER, Corpus Christi, TX 78408, Corpus Christi, TX, 78408
Construction50%

📊Project Metrics

TDLR #TABS2023004828
$210K
Project Value
6,000
Square Feet
$35/sqft
Cost/SqFt
6 months
Duration
Registered:Nov 7, 2022
Start:Dec 1, 2022
Target:May 19, 2023
📝

Review Complete

Design review complete, construction may proceed

📋Scope of Work

NEW TURNKEY 60 X 100 STORAGE BUILDING

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

📅Compliance Timeline

Project Registered
November 7, 2022
Construction Start
December 1, 2022
Expected Completion
May 19, 2023