🏁Project Closed🔧 Additions to Existing Building💵 This project is privately funded, on private land for private use.
New canopy for Trident Process Systems
2300 North I35, Gainesville, TX 76240, Gainesville, TX, 76240
Completed100%
📊Project Metrics
TDLR #TABS2023008216$65K
Project Value
1,116
Square Feet
$58/sqft
Cost/SqFt
3 months
Duration
Registered:Dec 22, 2022
Start:Feb 1, 2023
Target:May 1, 2023
🏁
Project Closed
Project has been completed and closed
📋Scope of Work
New roof canopy on the east side of the Trident Production Building. Open walls with the purpose to store raw materials to be accessed only by forklift.
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
📅Compliance Timeline
Project Registered
December 22, 2022
Construction Start
February 1, 2023
Expected Completion
May 1, 2023