🏁Project Closed🔧 Additions to Existing Building💵 This project involves public funds, public land, or is a Federally funded roadway project.
Stewart Elementary Hardening
4815 46th St, Lubbock, TX 79414, Lubbock, TX, 79414
Completed100%
📊Project Metrics
TDLR #TABS2023008870$700K
Project Value
2,000
Square Feet
$350/sqft
Cost/SqFt
6 months
Duration
Registered:Jan 6, 2023
Start:Feb 1, 2023
Target:Aug 1, 2023
🏁
Project Closed
Project has been completed and closed
📋Scope of Work
500 sq ft addition to existing facilities to provide a new reception area and secured entry. Existing reception area to receive new ceilings, finishes, and lighting as needed. New staff toilet facilities and kitchen area.
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
📅Compliance Timeline
Project Registered
January 6, 2023
Project Closed
August 1, 2023
Construction Start
February 1, 2023
Expected Completion
August 1, 2023