📝Review Complete🏗️ New Construction💵 This project is privately funded, on private land for private use.
Swift Sjolander
9001 Interstate Highway 10 East, Baytown, TX 77521, Baytown, TX, 77521
Construction50%
📊Project Metrics
TDLR #TABS2023014251$2.8M
Project Value
8,060
Square Feet
$347/sqft
Cost/SqFt
2y 4mo
Duration
Registered:Mar 16, 2023
Start:Aug 1, 2023
Target:Dec 1, 2025
📝
Review Complete
Design review complete, construction may proceed
📋Scope of Work
New 8,060 S.F. c-store with 5,160 S.F. car wash
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
📅Compliance Timeline
Project Registered
March 16, 2023
Construction Start
August 1, 2023
Expected Completion
December 1, 2025