๐Ÿ“Review Complete๐Ÿ”ง Renovation/Alteration๐Ÿ’ต This project involves public funds, public land, or is a Federally funded roadway project.

RFISD Rockport-Fulton HS Early Sitework Pkg

1801 Omohundro Street, Rockport, TX 78382, Rockport, TX, 78382
Construction50%

๐Ÿ“ŠProject Metrics

TDLR #TABS2023016390
$4.1M
Project Value
100
Square Feet
$41.48K/sqft
Cost/SqFt
3 months
Duration
Registered:Apr 12, 2023
Start:May 23, 2023
Target:Aug 9, 2023
๐Ÿ“

Review Complete

Design review complete, construction may proceed

๐Ÿ“‹Scope of Work

Site work including site utilities, grading, demolition and flatwork.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
April 12, 2023
Construction Start
May 23, 2023
Expected Completion
August 9, 2023