Dentist at Plumb Creek
Dentist at Plumb Creek is a new construction project at 400 Wetzel Drive, Kyle, in Hays County, TX, tracked from its Texas Department of Licensing and Regulation (TDLR) registration. Construction complete (TDLR inspection passed Feb 2024). The project has an estimated value of $850K across about 4,300 sq ft.
๐Project Metrics
TDLR #TABS2023017520Project Closed
Project has been completed and closed
Dentist at Plumb Creek is a New Construction project located at 400 Wetzel Drive, Kyle, TX 78640 in Kyle, Texas. The project has an estimated value of $850K covering 4,300 sq ft. Dr. Mahesh Dholariya is the property owner and Miller Architects, Inc. is the design firm of record. The project was registered with TDLR on April 25, 2023.
โFrequently Asked Questions
What is Dentist at Plumb Creek?
Dentist at Plumb Creek is a new construction project at 400 Wetzel Drive in Kyle, Texas, registered with the Texas Department of Licensing and Regulation (TDLR). Scope of work: Single story Dental Clinic with 1 additional lease suite
Is Dentist at Plumb Creek open in Kyle?
Construction on Dentist at Plumb Creek is complete โ TDLR records show the project passed its required accessibility inspection in Feb 2024. The building is finished and very likely open.
Where is Dentist at Plumb Creek located?
Dentist at Plumb Creek is located at 400 Wetzel Drive, Kyle, TX, 78640, in Hays County.
Who is the owner or developer of Dentist at Plumb Creek?
Dr. Mahesh Dholariya is the property owner/developer of record for Dentist at Plumb Creek, per its TDLR project registration.
Who is the architect or design firm for Dentist at Plumb Creek?
Miller Architects, Inc. is the design firm of record for Dentist at Plumb Creek, according to its TDLR filing.
How much does Dentist at Plumb Creek cost and how big is it?
Dentist at Plumb Creek has an estimated construction value of $850K and approximately 4,300 square feet (about $198/sqft), based on its TDLR filing.
๐Scope of Work
Single story Dental Clinic with 1 additional lease suite
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
๐ Project Timeline
Filed
Apr 25, 2023
Review Complete
Inspection Complete
Closed
Feb 1, 2024
๐Related Projects
๐๏ธSame Design Firm
$5.0M total๐Related City Permits
Building permits found at or near this location
Main breaker tripping for building need AE to provide emergency shutdown to investigate for connection issues and potential fault.
Installation of a 240 sf (8 ft x 30 ft) pre-fabricated aluminum covered walkway at the Eastside campus entrance to provide weather protection from the drop-off point to the building. Scope includes laying out and placing 6 concrete footings to support structural columns. All work to be completed per engineering specifications.
Installation of solar light poles around the existing playground area to increase security. 2026 015673 DA - Approved
Gas line to New Generator
Extend existing circuits from existing starline busway to 8) rows of benches in 5th floor lab. This scope of work was discussed and approved by Hyatt Dunn.
Property Owner
Design Firm
Registered Accessibility Specialist
Hays County Economy
Explore Area
Find Professionals
Need a contractor for this project?
Browse verified general contractors active in Hays County
Find General Contractors in Hays