๐Ÿ“Review Complete๐Ÿ”ง Renovation/Alteration๐Ÿ’ต This project involves public funds, public land, or is a Federally funded roadway project.

2021 Intersections Improvements

Intersections of Bowen Rd and Green Oaks/ New York, Arlington, TX 76017, Arlington, TX, 76017
Construction50%

๐Ÿ“ŠProject Metrics

TDLR #TABS2023021372
$190K
Project Value
9,500
Square Feet
$20/sqft
Cost/SqFt
2y 6mo
Duration
Registered:Jun 14, 2023
Start:Jun 14, 2023
Target:Dec 1, 2025
๐Ÿ“

Review Complete

Design review complete, construction may proceed

๐Ÿ“‹Scope of Work

This project primarily consists of constructing dedicated right turn lanes for the intersections of Bowen Road at Green Oaks Boulevard and New York Avenue and Green Oaks Boulevard. Improvements include concrete pavement, retaining walls, stormwater

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
June 14, 2023
Review Complete
June 14, 2023
Construction Start
June 14, 2023
Expected Completion
December 1, 2025

๐Ÿ”—Related Projects

Quick Actions

TDLR ID: TABS2023021372

Design Firm

๐Ÿ›๏ธ
Othon
View company profile
2140 Lake Park Boulevard Suite 200, Richardson, Texas 75080

Registered Accessibility Specialist

๐Ÿ“‹
GEORGE A,PATTERSON
RAS #503