Stassney Ln. from Teri Rd. to Burleson Rd.
📊Project Metrics
TDLR #TABS2023021694Project Closed
Project has been completed and closed
📋Scope of Work
Full depth road reconstruction including: cement stabilization; mill and overlay; storm drain utility improvements; installation of new curb and gutter; and new 8 Ft. - 11 Ft. wide shared use path along both sides of E. Stassney Ln.
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
📅Compliance Timeline
📄Related City Permits
Building permits found at or near this location
plug for water heater
Replacement of an existing water heater
Retro-Fit New TPO Roof system over existing roof. See system letter.
Retro-Fit New TPO Roof system over existing roof. See system letter.
New in ground pool (336sqft) w/ autofill and concrete decking (666 sqft)