โœ…Inspection Complete๐Ÿ—๏ธ New Construction๐Ÿ’ต This project is privately funded, on private land for private use.

Verizon Orange

3207 Edgar Brown Dr, West Orange, TX 77630, West Orange, TX, 77630
Final Inspection85%

๐Ÿ“ŠProject Metrics

TDLR #TABS2023022474
$600K
Project Value
3,000
Square Feet
$200/sqft
Cost/SqFt
6 months
Duration
Registered:Jun 28, 2023
Start:Sep 6, 2023
Target:Mar 6, 2024
โœ…

Inspection Complete

Final inspection completed, awaiting project closure

๐Ÿ“‹Scope of Work

Single Story shell only, building wood frame walls with wood trusses and plywood roof, concrete floor slab.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
June 28, 2023
Construction Start
September 6, 2023
Expected Completion
March 6, 2024