๐Ÿ“Review Complete๐Ÿ—๏ธ New Construction๐Ÿ’ต This project involves public funds, public land, or is a Federally funded roadway project.

Montrose Blvd - Segment 1

Montrose Blvd from Allen Parkway to W Clay Street, Houston, TX 77019, Houston, TX, 77019
Construction50%

๐Ÿ“ŠProject Metrics

TDLR #TABS2024000472
$12.4M
Project Value
287,700
Square Feet
$43/sqft
Cost/SqFt
1y 2mo
Duration
Registered:Sep 8, 2023
Start:May 1, 2025
Target:Jun 30, 2026
Remaining:127 days
๐Ÿ“

Review Complete

Design review complete, construction may proceed

๐Ÿ“‹Scope of Work

Full roadway reconstruction including traffic control, demolition, roadway, sidewalk, shared use path, retaining wall, pedestrian bridge, signing, striping, traffic signals, storm sewer, utilities, etc.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
September 8, 2023
Review Complete
September 8, 2023
Construction Start
May 1, 2025
Expected Completion
June 30, 2026

๐Ÿ“Location & Views

Open in MapsGet Directions|29.75535, -95.39711

Get alerts for Harris

Daily email when new projects start nearby.

Start Alerts - $19/mo

Download project data

Get curated lists of projects with full contact info.

Browse Data Lists