๐Ÿ“Review Complete๐Ÿ—๏ธ New Construction๐Ÿ’ต This project involves public funds, public land, or is a Federally funded roadway project.

SMITH COUNTY COURTHOUSE PHASE 1 - NEW PARKING GARAGE

210 E FERGUSON ST, Tyler, TX 75702, Tyler, TX, 75702
Construction50%

๐Ÿ“ŠProject Metrics

TDLR #TABS2024000521
$13.0M
Project Value
178,272
Square Feet
$73/sqft
Cost/SqFt
11 months
Duration
Registered:Sep 8, 2023
Start:Oct 1, 2023
Target:Aug 31, 2024
๐Ÿ“

Review Complete

Design review complete, construction may proceed

๐Ÿ“‹Scope of Work

THE PROJECT INCLUDES MINOR SITE DEMOLITION AND CONSTRUCTION OF A 5 LEVEL PARKING GARAGE.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
September 8, 2023
Construction Start
October 1, 2023
Expected Completion
August 31, 2024