๐Review Complete๐๏ธ New Construction๐ต This project is privately funded, on private land for private use.
Towne Twin Village - Phase III
4711 Dietrich, San Antonio, TX 78219, San Antonio, TX, 78219
Construction50%
๐Project Metrics
TDLR #TABS2024001624$7.5M
Project Value
52,064
Square Feet
$144/sqft
Cost/SqFt
3y 5mo
Duration
Registered:Sep 25, 2023
Start:Dec 15, 2023
Target:Apr 15, 2027
Remaining:474 days
๐
Review Complete
Design review complete, construction may proceed
๐Scope of Work
A new multi use community to include 4 new two story apartment buildings - F1, F2, F3, and F4. All 4 buildings are exactly the same. In each building there are 20 units 10 1st floor and 10 2nd floor. 1st floor - 6508 sq ft, 2nd floor 6508 sq ft.
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
September 25, 2023
Construction Start
December 15, 2023
Expected Completion
April 15, 2027
๐Related Projects
๐คSame Owner
$10.7M totalProperty Owner
๐ค
HFCC
Contact: Dr Chris Plauche
2 projects ยท $10.7M
View company profile
PO Box 831728, San Antonio, Texas 78283
Design Firm
๐๏ธ
Chesney Morales Partners
4 projects ยท $15.2M
View all projects
4901 Broadway, Suite 250, San Antonio, Texas 78209