DFW Terminal C Garage and Roadways Package 2
2330 North International Parkway, Dfw Airport, TX 75261, Dfw Airport, TX, 75261
Construction50%
๐Project Metrics
TDLR #TABS2024003004$25.0M
Project Value
650,351
Square Feet
$38/sqft
Cost/SqFt
1 year
Duration
Registered:Oct 12, 2023
Start:Jun 2, 2025
Target:May 29, 2026
Remaining:153 days
๐
Review Complete
Design review complete, construction may proceed
๐Scope of Work
Renovation of parking garage A at Terminal C
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
October 12, 2023
Construction Start
June 2, 2025
Expected Completion
May 29, 2026
๐Related Projects
๐คSame Owner
$18.4M totalProperty Owner
๐ค
Iliana Diaz
4 projects ยท $18.4M
View all projects
2330 North International Parkway, DFW Airport, Texas 75261
Design Firm
๐๏ธ
HOK
4 projects ยท $18.7M
View all projects
717 N. Harwood Street Suite 2850, Dallas, Texas 75201