Inspection Complete๐๏ธ New Construction๐ต This project is privately funded, on private land for private use.
Circle-K San El Paso, TX (NWC John Hayes & Edgemere)
NWC John Hayes & Edgemere Blvd, El Paso, TX 79938, El Paso, TX, 79938
Final Inspection85%
๐Project Metrics
TDLR #TABS2024007098$1.1M
Project Value
5,200
Square Feet
$202/sqft
Cost/SqFt
7 months
Duration
Registered:Dec 11, 2023
Start:Jul 22, 2024
Target:Feb 3, 2025
โ
Inspection Complete
Final inspection completed, awaiting project closure
๐Scope of Work
New construction including site work, new one story 5200 Sqft convenience store with new equipment, new signage, and a new fuel canopy structure.
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
December 11, 2023
Construction Start
July 22, 2024
Expected Completion
February 3, 2025
๐Related Projects
๐คSame Owner
$23.5M total๐๏ธSame Design Firm
$5.6M totalProperty Owner
๐ค
Circle K Stores Inc.
Contact: Adam Fullington
4 projects ยท $23.5M
View all projects
19500 Bulverde Rd Suite 100, San Antonio, Texas 78259
Design Firm
๐๏ธ
The Dimension Group
4 projects ยท $5.6M
View all projects
10755 Sandhill Rd., Dallas, Texas 75238