๐Project Closed๐๏ธ New Construction๐ต This project involves public funds, public land, or is a Federally funded roadway project.
WT Montgomery Road Phase 1A & 1B
5615 WT Montgomery Road (Quick Trip adjacent to the start of the project), San Antonio, TX 78252, San Antonio, TX, 78252
Completed100%
๐Project Metrics
TDLR #TABS2024007611$388K
Project Value
55,085
Square Feet
$7/sqft
Cost/SqFt
1y 7mo
Duration
Registered:Dec 18, 2023
Start:Aug 15, 2022
Target:Feb 29, 2024
๐
Project Closed
Project has been completed and closed
๐Scope of Work
Ph 1A is the reconstruction of the existing WT Montgomery Road north of US 90 to include bike lanes, curb, & sidewalk. Ph 1B is the extension of this roadway north of Freedom Way with a 4-lane facility with bike lanes, curb, & sidewalk.
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
December 18, 2023
Construction Start
August 15, 2022
Expected Completion
February 29, 2024
๐Related Projects
๐คSame Owner
$8.3M totalProperty Owner
๐ค
Bexar County
Contact: Jesse Garcia
4 projects ยท $8.3M
View all projects
1948 Probandt Street, San Antonio, Texas 78214
Design Firm
๐๏ธ
Cude Engineers
4 projects ยท $11.8M
View company profile
4122 Pond Hill Rd. Ste. 101, San Antonio, Texas 78231