๐Ÿ“‹Project Registered๐Ÿ”ง Renovation/Alteration๐Ÿ’ต This project is privately funded, on private land for private use.

MALLINCKRODT PHARMACEUTICALS

875 WEST SANDY LAKE ROAD SUITE 300, Coppell, TX 75019, Coppell, TX, 75019
Pre-Construction15%

๐Ÿ“ŠProject Metrics

TDLR #TABS2024007770
$120K
Project Value
8,477
Square Feet
$14/sqft
Cost/SqFt
2 months
Duration
Registered:Dec 19, 2023
Start:Jan 4, 2024
Target:Mar 4, 2024
๐Ÿ“‹

Project Registered

Project has been registered with TDLR and is in pre-construction phase

๐Ÿ“‹Scope of Work

559 SF AFFECTED AREA (8,477 TOTAL SF)

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
December 19, 2023
Construction Start
January 4, 2024
Expected Completion
March 4, 2024