Inspection Complete๐๏ธ New Construction๐ต This project is privately funded, on private land for private use.
307 Tenant Finish Out
5025 K Avenue, Suite 307, Plano, TX 75074, Plano, TX, 75074
Final Inspection85%
๐Project Metrics
TDLR #TABS2024012235$96K
Project Value
1,000
Square Feet
$96/sqft
Cost/SqFt
2 months
Duration
Registered:Feb 22, 2024
Start:Mar 15, 2024
Target:May 15, 2024
โ
Inspection Complete
Final inspection completed, awaiting project closure
๐Scope of Work
1st-time commercial finish out in a newly constructed shell building
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
February 22, 2024
Construction Start
March 15, 2024
Expected Completion
May 15, 2024
๐Related Projects
Property Owner
๐ค
Oak Point Plaza I, LLC
4 projects ยท $492K
View all projects
PO Box 427, Addison, Texas 75001