📝Review Complete🔧 Renovation/Alteration💵 This project is privately funded, on private land for private use.

Seal Master New Parking Lot

9421 Carnegie Ave., El Paso, TX 79925, El Paso, TX, 79925
Construction50%

📊Project Metrics

TDLR #TABS2024012833
$75K
Project Value
13,000
Square Feet
$6/sqft
Cost/SqFt
1 months
Duration
Registered:Mar 1, 2024
Start:Mar 11, 2024
Target:Mar 29, 2024
📝

Review Complete

Design review complete, construction may proceed

📋Scope of Work

New concrete parking lot entrance ramp, approximately 13,000 aq. ft. of new parking lot pavement with parking lot spaces paint stripping and approximately 3,000 sq. ft. of new landscaping areas.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

📅Compliance Timeline

Project Registered
March 1, 2024
Review Complete
March 1, 2024
Construction Start
March 11, 2024
Expected Completion
March 29, 2024