๐Ÿ“Review Complete๐Ÿ—๏ธ New Construction๐Ÿ’ต This project involves public funds, public land, or is a Federally funded roadway project.

D B Wood Road Phase 2

D B Wood Road to Oak Ridge Road to 800' South of Williams Drive, Georgetown, TX 78628, Georgetown, TX, 78628
Construction50%

๐Ÿ“ŠProject Metrics

TDLR #TABS2024015249
$30.5M
Project Value
60,050,074
Square Feet
$1/sqft
Cost/SqFt
2y 10mo
Duration
Registered:Apr 2, 2024
Start:Apr 11, 2025
Target:Feb 4, 2028
Remaining:702 days
๐Ÿ“

Review Complete

Design review complete, construction may proceed

๐Ÿ“‹Scope of Work

Design and construction of safety and mobility improvements including roadway widening, bridge widening, curb and gutter, sidewalk and pedestrian facilities, drainage systems and illumination. 60,050,074 s.f.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
April 2, 2024
Review Complete
April 2, 2024
Construction Start
April 11, 2025
Expected Completion
February 4, 2028

๐Ÿ“Location & Views

Open in MapsGet Directions|30.66922, -97.69709

Get alerts for Williamson

Daily email when new projects start nearby.

Start Alerts - $19/mo

Download project data

Get curated lists of projects with full contact info.

Browse Data Lists