๐Project Closed๐๏ธ New Construction๐ต This project involves public funds, public land, or is a Federally funded roadway project.
City of Cedar Park Sidewalk Gap Improvements Phase 6
Multiple locations throughout the City of Cedar Pa, Cedar Park, TX 78613, Cedar Park, TX, 78613
Completed100%
๐Project Metrics
TDLR #TABS2024016321$350K
Project Value
7,000
Square Feet
$50/sqft
Cost/SqFt
5 months
Duration
Registered:Apr 16, 2024
Start:May 1, 2024
Target:Oct 1, 2024
๐
Project Closed
Project has been completed and closed
๐Scope of Work
Construction of approximately 7,000 SF sidewalks, 16 curb ramps, 200 SF of driveways, 80 CY of retaining walls, asphalt paving and associated construction in response to City of Cedar Park planning and requests.
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
April 16, 2024
Construction Start
May 1, 2024
Expected Completion
October 1, 2024
๐Related Projects
๐คSame Owner
$42.6M totalProperty Owner
๐ค
City of Cedar Park
Contact: Tom Gdala
4 projects ยท $42.6M
View all projects
450 Cypress Creek Road Bldg. 1, Cedar Park, Texas 78613
Design Firm
๐๏ธ
Garver
4 projects ยท $18.7M
View all projects
285 SE Inner Loop Suite 110, Georgetown, Texas 78626