๐Project Closed๐ง Renovation/Alteration๐ต This project is privately funded, on private land for private use.
Cisco RCDN5 - Power Plant Upgrades
2250 E President George Bush Hwy, Bldg 5, Richardson, TX 75201, Richardson, TX, 75201
Completed100%
๐Project Metrics
TDLR #TABS2024016388$350K
Project Value
1,138
Square Feet
$308/sqft
Cost/SqFt
3 months
Duration
Registered:Apr 17, 2024
Start:Mar 8, 2024
Target:Jun 3, 2024
๐
Project Closed
Project has been completed and closed
๐Scope of Work
Demolish existing locker rooms and convert to new UPS/ESS Rm (new occupancy to be S-2 Storage). Demolish existing storage room and finish out new Mother's Rooms (new occupancy to be B Business).
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
April 17, 2024
Project Closed
June 3, 2024
Construction Start
March 8, 2024
Expected Completion
June 3, 2024
๐Related Projects
๐คSame Owner
$411K totalProperty Owner
๐ค
CISCO
Contact: Morganne Weaver
2 projects ยท $411K
View company profile