Building 56 Walkway, Balcony & Stairway Repairs

8350 Piney Shores Drive, Conroe, TX 77304, Conroe, TX, 77304
Construction50%

๐Ÿ“ŠProject Metrics

TDLR #TABS2024016940
$800K
Project Value
1,500
Square Feet
$533/sqft
Cost/SqFt
4 months
Duration
Registered:Apr 24, 2024
Start:Jun 1, 2024
Target:Sep 30, 2024
๐Ÿ“

Review Complete

Design review complete, construction may proceed

๐Ÿ“‹Scope of Work

Balcony, stair, and exterior walkway repairs - 1500 sqft

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
April 24, 2024
Construction Start
June 1, 2024
Expected Completion
September 30, 2024