๐Review Complete๐๏ธ New Construction๐ต This project involves public funds, public land, or is a Federally funded roadway project.
McKinney Fire Station No. 8
3445 Alma Road, Mckinney, TX 75070, Mckinney, TX, 75070
Construction50%
๐Project Metrics
TDLR #TABS2024017591$9.0M
Project Value
16,644
Square Feet
$541/sqft
Cost/SqFt
1y 2mo
Duration
Registered:May 2, 2024
Start:Dec 1, 2025
Target:Feb 1, 2027
Remaining:401 days
๐
Review Complete
Design review complete, construction may proceed
๐Scope of Work
New, 3 bay, fire station
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
May 2, 2024
Construction Start
December 1, 2025
Expected Completion
February 1, 2027
๐Related Projects
๐คSame Owner
$9.3M totalProperty Owner
๐ค
City of McKinney
Contact: Patricia Jackson, PE, RAS, Facility Construction Manager
4 projects ยท $9.3M
View all projects
3501 N. Central Expressway, McKinney, Texas 75071
Design Firm
๐๏ธ
CONDUIT ARCITECTURE DESIGN
4 projects ยท $5.8M
View company profile
711 N. Tennessee Street, McKinney, Texas 75069