McKinney Fire Station No. 8

3445 Alma Road, Mckinney, TX 75070, Mckinney, TX, 75070
Construction50%

๐Ÿ“ŠProject Metrics

TDLR #TABS2024017591
$9.0M
Project Value
16,644
Square Feet
$541/sqft
Cost/SqFt
1y 2mo
Duration
Registered:May 2, 2024
Start:Dec 1, 2025
Target:Feb 1, 2027
Remaining:401 days
๐Ÿ“

Review Complete

Design review complete, construction may proceed

๐Ÿ“‹Scope of Work

New, 3 bay, fire station

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
May 2, 2024
Construction Start
December 1, 2025
Expected Completion
February 1, 2027

Quick Actions

TDLR ID: TABS2024017591

Registered Accessibility Specialist

๐Ÿ“‹
JEFFERY L,KELLEY
RAS #55