✅Inspection Complete🔧 Renovation/Alteration💵 This project involves public funds, public land, or is a Federally funded roadway project.
Retama Parkway and Alton Boulevard Reconstruction
Retama Parkway, Selma, TX 78154, Selma, TX, 78154
Final Inspection85%
📊Project Metrics
TDLR #TABS2024019409$5.3M
Project Value
342,000
Square Feet
$16/sqft
Cost/SqFt
11 months
Duration
Registered:May 28, 2024
Start:Jul 1, 2024
Target:Jun 2, 2025
✅
Inspection Complete
Final inspection completed, awaiting project closure
📋Scope of Work
Reconstruction of the existing Retama Parkway asphalt pavement and reconstruction of the sidewalks located on the eastern side of Retama Parkway.
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
📅Compliance Timeline
Project Registered
May 28, 2024
Inspection Complete
June 2, 2025
Construction Start
July 1, 2024
Expected Completion
June 2, 2025
Property Owner
👤
City of Selma
Contact: Monique Vernon
View company profile
9375 Corporate Drive, Selma, Texas 78154