📝Review Complete🏗️ New Construction💵 This project is privately funded, on private land for private use.

SRM Ready Mix Terminal

103 Metrocrest Way, Terrell, TX 75160, Terrell, TX, 75160
Construction50%

📊Project Metrics

TDLR #TABS2024022001
$22.4M
Project Value
642,074
Square Feet
$35/sqft
Cost/SqFt
1y 2mo
Duration
Registered:Jun 28, 2024
Start:Aug 5, 2024
Target:Oct 5, 2025
📝

Review Complete

Design review complete, construction may proceed

📋Scope of Work

To upgrade the current ready mix terminal by adding a rail unloading system with a 40,000 ton cement storage dome and 600 ton cement silo that feeds two pneumatic truck loading systems.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

📅Compliance Timeline

Project Registered
June 28, 2024
Review Complete
June 28, 2024
Construction Start
August 5, 2024
Expected Completion
October 5, 2025